The increase in the number of electric vehicles and the development of sustainable mobility require the expansion of the charging infrastructure in accessible and relevant locations for users. In this context, ADREM designed and implemented for Auto Cobălcescu the infrastructure necessary to power a fast charging station for electric vehicles at the BMW dealership in Pitesti.
The project included complete design, power supply and equipment installation services, being developed to meet the charging requirements of the dealership’s customers and electric vehicle users in transit. The implemented solution was based on the Enel X Juice Pump Duo 60 charging station, an equipment designed for fast and simultaneous charging of electric vehicles.
To ensure the power supply of the station, a dedicated electrical infrastructure was built, including the execution of an underground low-voltage power line with a length of approximately 210 meters between the transformer substation and the site of the station. The works also included the construction of the earthing connection, the installation of the protection panel and the complete integration of the equipment into the existing electrical infrastructure.
The technical documentation and design were carried out by ADREM specialists, and the execution and commissioning works were carried out by the maintenance team from Argeș County. The implementation was carefully planned so that the activity of the representative office would not be affected, and the customers would benefit from uninterrupted access to the services offered throughout the duration of the works.
Completed in September 2021, the project contributes to the development of electromobility infrastructure in Argeș County and offers electric vehicle users access to a modern and efficient charging solution. Through this investment, Auto Cobălcescu strengthens its position as a promoter of sustainable mobility and technologies aimed at reducing environmental impact.
1 station
Enel X Juice Pump Duo 60 installed and commissioned
210 m
of underground power line made for power supply
3 days
for full implementation
60 kW
Power Charging Station